1.Good Practices for Scheduling
General Guidelines
The Project Schedule reflects the total project scope of work, as defined in the WBS, and should be scheduled to a level of granularity and detailedneeded to plan, implement, and control the project.
Documents Required before starting the scheduling process:
- The Project Scope
- WBS
- Resource Definition
In the Schedule Structure, the hierarchy must include:
- Higher level of the WBS
- Control accounts
- Work Packages and planning packages
- Activities.
Specific Guidelines
Define the list of schedule users, and responsibilities each user will have (Provide progress, read-only, administrative functions, etc).
Define a default project calendar.
Define the project update cycle in which the current status is reported.
Identification of resources necessary to accomplish activities (human, machines, materials, location, etc)
Define Milestones.
Each activity should have a owner, description, duration.
Every activity and milestone should be connected to at least one predecessor and one succesor activity, with the exception of the start milestone.
A preceeding activity needs to finish or start prior to any activity starting.
Lags should only be used to represent delays that are physically necessary, represent no work, and have duration but no resource assigned.
WBS Levels Guidelines
Schedule levels are to be specified by the project team. Each level has a general purpose and content:
Level 0- Project Summary,
Level 1- Executive Summary,
Level 2- Management Summary (interfaces between key deliverables and project participants;
Level 3- Publication schedule: interfaces between key workgroups, disciplines, crafts involved. It is helpful to identify critical paths and activities that could affect the outcome of a phase or stage.
Level 4- Execution Planning: reflects the interfaces between key elements that drive the completion of activities.
Level 5- Detailed planning: To communicate task requirements for completing activities identified in a detailed schedule. Duration is usually 1 day to 1 week. This level is used to plan and schedule use of resources (labor, equipment, and materials).
Schedule Execution Guidelines
Collect actuals and remaining work or duration.
Update the schedule model according to the actuals.
Compare and address any deviation: Compare to the stored baseline.
Update the schedule model with approved changes.
Update the baseline schedule model, when it is impacted by major scope changes.
Communicate when a update cycle is completed.
Process Outputs